Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in South Chicago

The typical renovation & alteration permit issued in South Chicago took 36 days. The 75th-percentile wait was 98 days.

Records checked3582021–Sep. 15, 2026

The short answer

Typical wait36 daysmedian issued permit
Usually within98 days75% of records
Long-wait edge191 days90% of records
Evidence358issued permits

The median was 2.5 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
19.0%
1–7 days
15.9%
8–30 days
10.9%
31–90 days
27.9%
91+ days
26.3%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021795 days51 days104 days
2022886 days78 days170 days
20236129 days80 days196 days
20245255 days116 days173 days
20254465 days136 days284 days
2026*3482 days165 days266 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
South Chicago36 days98 days358
Calumet Heights36 days86 days133
Garfield Ridge37 days95 days274
Logan Square36 days100 days1,286
South Deering36 days113 days85
Uptown37 days89 days519
West Town36 days97 days1,728
Beverly36 days91 days308