The typical renovation & alteration permit issued in South Chicago took 36 days. The 75th-percentile wait was 98 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in South Chicago, 358 issued permit records show a median processing time of 36 days; 75% were issued within 98 days and 90% within 191 days, covering January 2021 through September 15, 2026.
The median was 2.5 days slower than the previous 12 months.
Renovation & Alteration permits in South Chicago: wait distribution
For Renovation & Alteration permits in South Chicago, 358 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in South Chicago: annual permit timing
Renovation & Alteration permits in South Chicago has 6 publishable issue-year cohorts spanning 2021–2026, representing 358 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 79 | 5 days | 51 days | 104 days |
| 2022 | 88 | 6 days | 78 days | 170 days |
| 2023 | 61 | 29 days | 80 days | 196 days |
| 2024 | 52 | 55 days | 116 days | 173 days |
| 2025 | 44 | 65 days | 136 days | 284 days |
| 2026* | 34 | 82 days | 165 days | 266 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in South Chicago: Renovation & Alteration timing in comparable community areas
Renovation & Alteration permits in South Chicago has 358 issued records, a 36 days median, and a 98 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| South Chicago | 36 days | 98 days | 358 |
| Calumet Heights | 36 days | 86 days | 133 |
| Garfield Ridge | 37 days | 95 days | 274 |
| Logan Square | 36 days | 100 days | 1,286 |
| South Deering | 36 days | 113 days | 85 |
| Uptown | 37 days | 89 days | 519 |
| West Town | 36 days | 97 days | 1,728 |
| Beverly | 36 days | 91 days | 308 |
More Renovation & Alteration permits in South Chicago comparisons
The Renovation & Alteration permits in South Chicago cohort contains 358 issued records; related links retain separate location and permit-category cohorts.
All South Chicago permits Area reportRenovation & Alteration citywide Type report