Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Official community area

South Chicago permit processing times

For 1,851 issued permits in South Chicago, the median processing time was 1 day; 75% were issued within 13 days.

Records checked1,8512021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within13 days75% of records
Long-wait edge64 days90% of records
Evidence1,851issued permits

The median was 1 day slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
48.5%
1–7 days
19.8%
8–30 days
15.2%
31–90 days
8.9%
91+ days
7.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20213710 days7 days59 days
20223760 days5 days50 days
20232960 days13 days56 days
20243044 days18 days77 days
20252884 days21 days82 days
2026*2165 days24 days75 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Nearby points in the citywide timing distribution

ReportMedian75% withinRecords
Albany Park1 day14 days2,213
Archer Heights1 day14 days812
Ashburn1 day10 days2,411
Auburn Gresham1 day11 days3,290
Austin1 day14 days5,647
Belmont Cragin1 day13 days2,724
Beverly1 day13 days1,644
Burnside1 day9.5 days227