Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Signs permits in South Chicago

The typical signs permit issued in South Chicago took 18 days. The 75th-percentile wait was 120 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked422021–Sep. 15, 2026

The short answer

For Signs permits in South Chicago, 42 issued permit records show a median processing time of 18 days; 75% were issued within 120 days and 90% within 150 days, covering January 2021 through September 15, 2026.

Typical wait18 daysmedian issued permit
Usually within120 days75% of records
Long-wait edge150 days90% of records
Evidence42issued permits

Not enough records for a year-over-year comparison.

Signs permits in South Chicago: wait distribution

For Signs permits in South Chicago, 42 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
0.0%
1–7 days
26.2%
8–30 days
28.6%
31–90 days
9.5%
91+ days
35.7%

Change over time

Signs permits in South Chicago: annual permit timing

Signs permits in South Chicago has 2 publishable issue-year cohorts spanning 2021–2022, representing 24 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211026 days54 days151 days
2022145 days150 days158 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs permits in South Chicago: Signs timing in comparable community areas

Signs permits in South Chicago has 42 issued records, a 18 days median, and a 120 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
South Chicago18 days120 days42
Austin19 days65 days293
South Lawndale18 days55 days225
West Town19 days57 days889
Auburn Gresham18 days37 days84
Irving Park20 days44 days230
East Garfield Park17 days47 days42
New City20 days54 days126