Community area × permit type

Renovation & Alteration permits in Garfield Ridge

The typical renovation & alteration permit issued in Garfield Ridge took 37 days. The 75th-percentile wait was 95 days.

Records checked2742021–Sep. 15, 2026

The short answer

Typical wait37 daysmedian issued permit
Usually within95 days75% of records
Long-wait edge202 days90% of records
Evidence274issued permits

The median was 23 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
25.2%
1–7 days
9.5%
8–30 days
10.2%
31–90 days
29.9%
91+ days
25.2%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20214825 days66 days139 days
2022641.5 days84 days166 days
2023564.5 days46 days96 days
20244372 days170 days262 days
20253362 days154 days292 days
2026*3062 days98 days146 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Garfield Ridge37 days95 days274
Uptown37 days89 days519
South Chicago36 days98 days358
Calumet Heights36 days86 days133
Hegewisch38 days132 days54
Logan Square36 days100 days1,286
South Deering36 days113 days85
West Town36 days97 days1,728