Wrecking & Demolition permits in ZIP 60639

The median wrecking & demolition permit wait in ZIP 60639 was 0 days, based on 26 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked262021–Sep. 15, 2026

The short answer

For Wrecking & Demolition permits in ZIP 60639, 26 issued permit records show a median processing time of 0 days; 75% were issued within 42 days and 90% within 62 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within42 days75% of records
Long-wait edge62 days90% of records
Evidence26issued permits

Not enough records for a year-over-year comparison.

Wrecking & Demolition permits in ZIP 60639: wait distribution

For Wrecking & Demolition permits in ZIP 60639, 26 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
69.2%
1–7 days
0.0%
8–30 days
3.8%
31–90 days
19.2%
91+ days
7.7%

Change over time

Wrecking & Demolition permits in ZIP 60639: annual permit timing

Wrecking & Demolition permits in ZIP 60639 has 0 publishable issue-year cohorts spanning no qualifying years, representing 0 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Wrecking & Demolition permits in ZIP 60639: Wrecking & Demolition timing in comparable ZIP codes

Wrecking & Demolition permits in ZIP 60639 has 26 issued records, a 0 days median, and a 42 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606070 days70 days89
ZIP 606080 days64 days115
ZIP 606090 days48 days151
ZIP 606120 days58 days95
ZIP 606130 days51 days128
ZIP 606140 days60 days270
ZIP 606160 days55 days53
ZIP 606170 days24 days118