ZIP code × permit type
Wrecking & Demolition permits in ZIP 60622
The median wrecking & demolition permit wait in ZIP 60622 was 0 days, based on 173 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Wrecking & Demolition permits in ZIP 60622, 173 issued permit records show a median processing time of 0 days; 75% were issued within 51 days and 90% within 87 days, covering January 2021 through September 15, 2026.
The median was 26 days slower than the previous 12 months.
Wrecking & Demolition permits in ZIP 60622: wait distribution
For Wrecking & Demolition permits in ZIP 60622, 173 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Wrecking & Demolition permits in ZIP 60622: annual permit timing
Wrecking & Demolition permits in ZIP 60622 has 6 publishable issue-year cohorts spanning 2021–2026, representing 173 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 31 | 55 days | 88 days | 107 days |
| 2022 | 32 | 0 days | 55 days | 87 days |
| 2023 | 32 | 0 days | 0 days | 0 days |
| 2024 | 20 | 0 days | 0 days | 0 days |
| 2025 | 32 | 0 days | 0 days | 0 days |
| 2026* | 26 | 52 days | 72 days | 92 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Wrecking & Demolition permits in ZIP 60622: Wrecking & Demolition timing in comparable ZIP codes
Wrecking & Demolition permits in ZIP 60622 has 173 issued records, a 0 days median, and a 51 days 75th-percentile wait in this release.
More Wrecking & Demolition permits in ZIP 60622 comparisons
The Wrecking & Demolition permits in ZIP 60622 cohort contains 173 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60622 permits ZIP reportWrecking & Demolition citywide Type report