ZIP code × permit type

Express Permit Program permits in ZIP 60620

The median express permit program permit wait in ZIP 60620 was 1 day, based on 2,586 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked2,5862021–Sep. 15, 2026

The short answer

For Express Permit Program permits in ZIP 60620, 2,586 issued permit records show a median processing time of 1 day; 75% were issued within 7 days and 90% within 18 days, covering January 2021 through September 15, 2026.

Typical wait1 daymedian issued permit
Usually within7 days75% of records
Long-wait edge18 days90% of records
Evidence2,586issued permits

The median was 1 day slower than the previous 12 months.

Express Permit Program permits in ZIP 60620: wait distribution

For Express Permit Program permits in ZIP 60620, 2,586 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
47.3%
1–7 days
29.3%
8–30 days
18.1%
31–90 days
4.0%
91+ days
1.3%

Change over time

Express Permit Program permits in ZIP 60620: annual permit timing

Express Permit Program permits in ZIP 60620 has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,586 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20213230 days1 day9 days
20222990 days1 day6.2 days
20232840 days5 days21 days
20245861 day6 days17 days
20256343 days9 days20 days
2026*4603 days11 days22 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in ZIP 60620: Express Permit Program timing in comparable ZIP codes

Express Permit Program permits in ZIP 60620 has 2,586 issued records, a 1 day median, and a 7 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606021 day9 days1,021
ZIP 606031 day9 days1,124
ZIP 606051 day10 days1,055
ZIP 606081 day7 days1,903
ZIP 606091 day7 days1,621
ZIP 606121 day7 days1,543
ZIP 606131 day8 days1,095
ZIP 606141 day9 days2,934