Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Wrecking & Demolition permits in ZIP 60642

The median wrecking & demolition permit wait in ZIP 60642 was 0 days, based on 67 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked672021–Sep. 15, 2026

The short answer

For Wrecking & Demolition permits in ZIP 60642, 67 issued permit records show a median processing time of 0 days; 75% were issued within 72 days and 90% within 95 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within72 days75% of records
Long-wait edge95 days90% of records
Evidence67issued permits

Not enough records for a year-over-year comparison.

Wrecking & Demolition permits in ZIP 60642: wait distribution

For Wrecking & Demolition permits in ZIP 60642, 67 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
53.7%
1–7 days
1.5%
8–30 days
3.0%
31–90 days
22.4%
91+ days
19.4%

Change over time

Wrecking & Demolition permits in ZIP 60642: annual permit timing

Wrecking & Demolition permits in ZIP 60642 has 4 publishable issue-year cohorts spanning 2021–2026, representing 55 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20212131 days77 days96 days
20221155 days120 days146 days
2024130 days0 days61 days
2026*1074 days92 days96 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Wrecking & Demolition permits in ZIP 60642: Wrecking & Demolition timing in comparable ZIP codes

Wrecking & Demolition permits in ZIP 60642 has 67 issued records, a 0 days median, and a 72 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606070 days70 days89
ZIP 606080 days64 days115
ZIP 606090 days48 days151
ZIP 606120 days58 days95
ZIP 606130 days51 days128
ZIP 606140 days60 days270
ZIP 606160 days55 days53
ZIP 606170 days24 days118