Express Permit Program permits in ZIP 60641
The median express permit program permit wait in ZIP 60641 was 0 days, based on 1,619 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Express Permit Program permits in ZIP 60641, 1,619 issued permit records show a median processing time of 0 days; 75% were issued within 6 days and 90% within 18 days, covering January 2021 through September 15, 2026.
The median was 2 days faster than the previous 12 months.
Express Permit Program permits in ZIP 60641: wait distribution
For Express Permit Program permits in ZIP 60641, 1,619 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Express Permit Program permits in ZIP 60641: annual permit timing
Express Permit Program permits in ZIP 60641 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,619 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 200 | 0 days | 0 days | 17 days |
| 2022 | 161 | 0 days | 0 days | 20 days |
| 2023 | 176 | 0 days | 3 days | 14 days |
| 2024 | 436 | 1 day | 6 days | 19 days |
| 2025 | 382 | 2 days | 8 days | 15 days |
| 2026* | 264 | 1 day | 7 days | 19 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Express Permit Program permits in ZIP 60641: Express Permit Program timing in comparable ZIP codes
Express Permit Program permits in ZIP 60641 has 1,619 issued records, a 0 days median, and a 6 days 75th-percentile wait in this release.
More Express Permit Program permits in ZIP 60641 comparisons
The Express Permit Program permits in ZIP 60641 cohort contains 1,619 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60641 permits ZIP reportExpress Permit Program citywide Type report