ZIP code × permit type
Scaffolding permits in ZIP 60603
The median scaffolding permit wait in ZIP 60603 was 0 days, based on 35 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Scaffolding permits in ZIP 60603, 35 issued permit records show a median processing time of 0 days; 75% were issued within 1 day and 90% within 6.2 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
Scaffolding permits in ZIP 60603: wait distribution
For Scaffolding permits in ZIP 60603, 35 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Scaffolding permits in ZIP 60603: annual permit timing
Scaffolding permits in ZIP 60603 has 2 publishable issue-year cohorts spanning 2021–2022, representing 27 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 14 | 0 days | 0.8 days | 5.2 days |
| 2022 | 13 | 0 days | 4 days | 5 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Scaffolding permits in ZIP 60603: Scaffolding timing in comparable ZIP codes
Scaffolding permits in ZIP 60603 has 35 issued records, a 0 days median, and a 1 day 75th-percentile wait in this release.
More Scaffolding permits in ZIP 60603 comparisons
The Scaffolding permits in ZIP 60603 cohort contains 35 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60603 permits ZIP reportScaffolding citywide Type report