Express Permit Program permits in West Garfield Park

The typical express permit program permit issued in West Garfield Park took 1 day. The 75th-percentile wait was 7 days.

Records checked5582021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within7 days75% of records
Long-wait edge20 days90% of records
Evidence558issued permits

The median was unchanged from the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
46.1%
1–7 days
30.3%
8–30 days
17.6%
31–90 days
5.2%
91+ days
0.9%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021940 days0 days1.7 days
2022690 days0 days0.2 days
2023530 days1 day7.6 days
20241142 days11 days28 days
20251325 days14 days27 days
2026*964 days10 days22 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Albany Park1 day6 days997
Auburn Gresham1 day7 days1,679
Austin1 day7 days2,565
Avondale1 day6 days866
Beverly1 day7 days843
Brighton Park1 day9 days684
Burnside1 day5 days127
Chatham1 day7 days1,207