Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Official community area

West Garfield Park permit processing times

For 1,357 issued permits in West Garfield Park, the median processing time was 1 day; 75% were issued within 16 days.

Records checked1,3572021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within16 days75% of records
Long-wait edge82 days90% of records
Evidence1,357issued permits

The median was 2.5 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
48.0%
1–7 days
19.6%
8–30 days
12.6%
31–90 days
10.8%
91+ days
9.1%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20213160 days4 days58 days
20222660 days1 day40 days
20232130 days7 days50 days
20242066 days47 days116 days
20252148 days39 days89 days
2026*1426 days28 days86 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Nearby points in the citywide timing distribution

ReportMedian75% withinRecords
Albany Park1 day14 days2,213
Archer Heights1 day14 days812
Ashburn1 day10 days2,411
Auburn Gresham1 day11 days3,290
Austin1 day14 days5,647
Belmont Cragin1 day13 days2,724
Beverly1 day13 days1,644
Burnside1 day9.5 days227