Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Washington Heights

The typical renovation & alteration permit issued in Washington Heights took 49 days. The 75th-percentile wait was 106 days.

Records checked2412021–Sep. 15, 2026

The short answer

Typical wait49 daysmedian issued permit
Usually within106 days75% of records
Long-wait edge185 days90% of records
Evidence241issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
19.9%
1–7 days
8.7%
8–30 days
10.8%
31–90 days
31.1%
91+ days
29.5%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021484.5 days68 days150 days
20226622 days70 days193 days
20233441 days126 days202 days
20244269 days110 days148 days
20253269 days109 days231 days
2026*1995 days116 days164 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Washington Heights49 days106 days241
Archer Heights48 days104 days109
Belmont Cragin48 days117 days389
Forest Glen50 days107 days256
Lower West Side48 days118 days560
South Lawndale48 days115 days504
Near South Side48 days106 days238
Ashburn51 days118 days207