Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Signs permits in Near West Side

The typical signs permit issued in Near West Side took 29 days. The 75th-percentile wait was 75 days.

Records checked1,1832021–Sep. 15, 2026

The short answer

Typical wait29 daysmedian issued permit
Usually within75 days75% of records
Long-wait edge150 days90% of records
Evidence1,183issued permits

The median was 11 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
2.1%
1–7 days
17.2%
8–30 days
32.5%
31–90 days
27.6%
91+ days
20.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
202120523 days121 days357 days
202220010 days35 days103 days
202323820 days49 days142 days
202419945 days74 days174 days
202520834 days80 days123 days
2026*13355 days95 days139 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs timing in comparable community areas

ReportMedian75% withinRecords
Hermosa29 days57 days82
Lake View29 days67 days728
Near West Side29 days75 days1,183
Uptown29 days64 days212
Bridgeport28 days91 days97
Woodlawn28 days74 days40
Armour Square26 days47 days50
Near North Side32 days69 days1,501