Signs permits in Uptown

The typical signs permit issued in Uptown took 29 days. The 75th-percentile wait was 64 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked2122021–Sep. 15, 2026

The short answer

For Signs permits in Uptown, 212 issued permit records show a median processing time of 29 days; 75% were issued within 64 days and 90% within 133 days, covering January 2021 through September 15, 2026.

Typical wait29 daysmedian issued permit
Usually within64 days75% of records
Long-wait edge133 days90% of records
Evidence212issued permits

The median was 14 days faster than the previous 12 months.

Signs permits in Uptown: wait distribution

For Signs permits in Uptown, 212 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
0.5%
1–7 days
18.4%
8–30 days
36.3%
31–90 days
29.7%
91+ days
15.1%

Change over time

Signs permits in Uptown: annual permit timing

Signs permits in Uptown has 6 publishable issue-year cohorts spanning 2021–2026, representing 212 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211970 days276 days559 days
20222510 days41 days74 days
2023569.5 days34 days66 days
20245122 days41 days155 days
20253449 days76 days135 days
2026*2730 days65 days111 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs permits in Uptown: Signs timing in comparable community areas

Signs permits in Uptown has 212 issued records, a 29 days median, and a 64 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Hermosa29 days57 days82
Lake View29 days67 days728
Near West Side29 days75 days1,183
Uptown29 days64 days212
Bridgeport28 days91 days97
Woodlawn28 days74 days40
Armour Square26 days47 days50
Near North Side32 days69 days1,501