Near West Side permit processing times
For 10,466 issued permits in Near West Side, the median processing time was 2 days; 75% were issued within 21 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Near West Side permit processing times, 10,466 issued permit records show a median processing time of 2 days; 75% were issued within 21 days and 90% within 74 days, covering January 2021 through September 15, 2026.
The median was 1 day faster than the previous 12 months.
Near West Side permit processing times: wait distribution
For Near West Side permit processing times, 10,466 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Near West Side permit processing times: annual permit timing
Near West Side permit processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 10,466 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 1,999 | 0 days | 14 days | 67 days |
| 2022 | 2,141 | 0 days | 14 days | 59 days |
| 2023 | 2,008 | 1 day | 20 days | 71 days |
| 2024 | 1,628 | 8 days | 32 days | 82 days |
| 2025 | 1,544 | 6 days | 24 days | 82 days |
| 2026* | 1,146 | 6 days | 28 days | 90 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Near West Side permit processing times: Nearby points in the citywide timing distribution
Near West Side permit processing times has 10,466 issued records, a 2 days median, and a 21 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Avondale | 2 days | 21 days | 2,361 |
| Bridgeport | 2 days | 24 days | 1,920 |
| Brighton Park | 2 days | 19 days | 1,507 |
| Englewood | 2 days | 24 days | 2,131 |
| Lake View | 2 days | 23 days | 6,844 |
| Logan Square | 2 days | 29 days | 5,067 |
| Loop | 2 days | 15 days | 15,467 |
| Lower West Side | 2 days | 31 days | 2,358 |
More Near West Side permit processing times comparisons
The Near West Side permit processing times cohort contains 10,466 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 8 daysSigns 29 daysEasy Permit Process 0 daysNew Construction 16 daysElevator Equipment 0 daysWrecking & Demolition 0 daysScaffolding 0 daysReinstated Permit 0 days