Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Elevator Equipment permits in ZIP 60638

The median elevator equipment permit wait in ZIP 60638 was 0 days, based on 30 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked302021–Sep. 15, 2026

The short answer

For Elevator Equipment permits in ZIP 60638, 30 issued permit records show a median processing time of 0 days; 75% were issued within 0 days and 90% within 0 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within0 days75% of records
Long-wait edge0 days90% of records
Evidence30issued permits

Not enough records for a year-over-year comparison.

Elevator Equipment permits in ZIP 60638: wait distribution

For Elevator Equipment permits in ZIP 60638, 30 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
93.3%
1–7 days
3.3%
8–30 days
3.3%
31–90 days
0.0%
91+ days
0.0%

Change over time

Elevator Equipment permits in ZIP 60638: annual permit timing

Elevator Equipment permits in ZIP 60638 has 0 publishable issue-year cohorts spanning no qualifying years, representing 0 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Elevator Equipment permits in ZIP 60638: Elevator Equipment timing in comparable ZIP codes

Elevator Equipment permits in ZIP 60638 has 30 issued records, a 0 days median, and a 0 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606010 days5 days290
ZIP 606020 days5 days113
ZIP 606030 days5 days147
ZIP 606040 days0 days90
ZIP 606050 days4 days187
ZIP 606060 days5 days240
ZIP 606070 days1 day240
ZIP 606080 days0 days146