Community area × permit type
Express Permit Program permits in West Pullman
The typical express permit program permit issued in West Pullman took 1 day. The 75th-percentile wait was 6 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Express Permit Program permits in West Pullman, 1,124 issued permit records show a median processing time of 1 day; 75% were issued within 6 days and 90% within 13 days, covering January 2021 through September 15, 2026.
The median was 2 days slower than the previous 12 months.
Express Permit Program permits in West Pullman: wait distribution
For Express Permit Program permits in West Pullman, 1,124 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Express Permit Program permits in West Pullman: annual permit timing
Express Permit Program permits in West Pullman has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,124 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 131 | 0 days | 1 day | 3 days |
| 2022 | 111 | 0 days | 0 days | 6 days |
| 2023 | 146 | 0 days | 1.8 days | 12 days |
| 2024 | 275 | 1 day | 5 days | 13 days |
| 2025 | 259 | 3 days | 9.5 days | 19 days |
| 2026* | 202 | 3 days | 8 days | 15 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Express Permit Program permits in West Pullman: Express Permit Program timing in comparable community areas
Express Permit Program permits in West Pullman has 1,124 issued records, a 1 day median, and a 6 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Albany Park | 1 day | 6 days | 997 |
| Auburn Gresham | 1 day | 7 days | 1,679 |
| Austin | 1 day | 7 days | 2,565 |
| Avondale | 1 day | 6 days | 866 |
| Beverly | 1 day | 7 days | 843 |
| Brighton Park | 1 day | 9 days | 684 |
| Burnside | 1 day | 5 days | 127 |
| Chatham | 1 day | 7 days | 1,207 |
More Express Permit Program permits in West Pullman comparisons
The Express Permit Program permits in West Pullman cohort contains 1,124 issued records; related links retain separate location and permit-category cohorts.
All West Pullman permits Area reportExpress Permit Program citywide Type report