Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Express Permit Program permits in West Englewood

The typical express permit program permit issued in West Englewood took 1 day. The 75th-percentile wait was 6 days.

Records checked1,0252021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within6 days75% of records
Long-wait edge16 days90% of records
Evidence1,025issued permits

The median was unchanged from the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
47.2%
1–7 days
30.9%
8–30 days
17.1%
31–90 days
3.9%
91+ days
0.9%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211500 days0 days3.3 days
20221050 days0 days3.8 days
20231250 days1 day4 days
20242251 day8 days22 days
20252544 days9 days19 days
2026*1665 days13 days28 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Albany Park1 day6 days997
Auburn Gresham1 day7 days1,679
Austin1 day7 days2,565
Avondale1 day6 days866
Beverly1 day7 days843
Brighton Park1 day9 days684
Burnside1 day5 days127
Chatham1 day7 days1,207