Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Express Permit Program permits in Washington Heights

The typical express permit program permit issued in Washington Heights took 1 day. The 75th-percentile wait was 6 days.

Records checked1,1542021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within6 days75% of records
Long-wait edge15 days90% of records
Evidence1,154issued permits

The median was 2 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
48.2%
1–7 days
30.8%
8–30 days
16.4%
31–90 days
3.5%
91+ days
1.2%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211300 days1 day6.1 days
20221340 days1 day8 days
2023990 days2 days19 days
20242581 day5.8 days14 days
20253061 day8 days18 days
2026*2273 days9 days20 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Albany Park1 day6 days997
Auburn Gresham1 day7 days1,679
Austin1 day7 days2,565
Avondale1 day6 days866
Beverly1 day7 days843
Brighton Park1 day9 days684
Burnside1 day5 days127
Chatham1 day7 days1,207