Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Express Permit Program permits in South Lawndale

The typical express permit program permit issued in South Lawndale took 1 day. The 75th-percentile wait was 8 days.

Records checked9802021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within8 days75% of records
Long-wait edge22 days90% of records
Evidence980issued permits

The median was 1 day faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
42.8%
1–7 days
32.0%
8–30 days
17.9%
31–90 days
5.8%
91+ days
1.5%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211420 days0 days7.9 days
20221020 days0 days8.9 days
20231340 days3 days27 days
20242053 days10 days24 days
20252303 days12 days22 days
2026*1673 days11 days24 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Albany Park1 day6 days997
Auburn Gresham1 day7 days1,679
Austin1 day7 days2,565
Avondale1 day6 days866
Beverly1 day7 days843
Brighton Park1 day9 days684
Burnside1 day5 days127
Chatham1 day7 days1,207