Official community area
New City permit processing times
For 2,436 issued permits in New City, the median processing time was 2 days; 75% were issued within 26 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New City permit processing times, 2,436 issued permit records show a median processing time of 2 days; 75% were issued within 26 days and 90% within 113 days, covering January 2021 through September 15, 2026.
The median was 7 days faster than the previous 12 months.
New City permit processing times: wait distribution
For New City permit processing times, 2,436 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New City permit processing times: annual permit timing
New City permit processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,436 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 463 | 0 days | 11 days | 79 days |
| 2022 | 478 | 0 days | 5 days | 69 days |
| 2023 | 399 | 0 days | 13 days | 86 days |
| 2024 | 375 | 12 days | 43 days | 163 days |
| 2025 | 418 | 11 days | 42 days | 142 days |
| 2026* | 303 | 7 days | 43 days | 136 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New City permit processing times: Nearby points in the citywide timing distribution
New City permit processing times has 2,436 issued records, a 2 days median, and a 26 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Avondale | 2 days | 21 days | 2,361 |
| Bridgeport | 2 days | 24 days | 1,920 |
| Brighton Park | 2 days | 19 days | 1,507 |
| Englewood | 2 days | 24 days | 2,131 |
| Lake View | 2 days | 23 days | 6,844 |
| Logan Square | 2 days | 29 days | 5,067 |
| Loop | 2 days | 15 days | 15,467 |
| Lower West Side | 2 days | 31 days | 2,358 |
More New City permit processing times comparisons
The New City permit processing times cohort contains 2,436 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 44 daysEasy Permit Process 0 daysSigns 20 daysNew Construction 118 daysWrecking & Demolition 0 daysElevator Equipment 0 daysReinstated Permit 0 days