Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Express Permit Program permits in Englewood

The typical express permit program permit issued in Englewood took 1 day. The 75th-percentile wait was 8 days.

Records checked8482021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within8 days75% of records
Long-wait edge24 days90% of records
Evidence848issued permits

The median was unchanged from the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
44.6%
1–7 days
28.5%
8–30 days
20.0%
31–90 days
5.5%
91+ days
1.3%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211390 days0.5 days6 days
20221120 days0 days8 days
2023850 days1 day6.6 days
20241862 days14 days26 days
20251835 days16 days39 days
2026*1435 days14 days28 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Albany Park1 day6 days997
Auburn Gresham1 day7 days1,679
Austin1 day7 days2,565
Avondale1 day6 days866
Beverly1 day7 days843
Brighton Park1 day9 days684
Burnside1 day5 days127
Chatham1 day7 days1,207