Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Express Permit Program permits in Woodlawn

The typical express permit program permit issued in Woodlawn took 2 days. The 75th-percentile wait was 9 days.

Records checked9202021–Sep. 15, 2026

The short answer

Typical wait2 daysmedian issued permit
Usually within9 days75% of records
Long-wait edge28 days90% of records
Evidence920issued permits

The median was 2 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
39.5%
1–7 days
31.8%
8–30 days
20.1%
31–90 days
6.6%
91+ days
2.0%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211530 days1 day15 days
20221050 days0 days6 days
20231271 day17 days62 days
20242124 days13 days30 days
20251945 days14 days28 days
2026*1292 days8 days22 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Bridgeport2 days8.2 days692
East Garfield Park2 days8 days616
Grand Boulevard2 days9 days676
Loop2 days15 days9,444
Montclare2 days10 days294
North Lawndale2 days8 days1,020
Uptown2 days10 days1,063
West Town2 days12 days2,616