Easy Permit Process permits in Pullman
The typical easy permit process permit issued in Pullman took 1 day. The 75th-percentile wait was 12 days.
Records checked1092021–Sep. 15, 2026
The short answer
Typical wait1 daymedian issued permit
Usually within12 days75% of records
Long-wait edge21 days90% of records
Evidence109issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 36 | 1.5 days | 13 days | 47 days |
| 2022 | 45 | 0 days | 12 days | 18 days |
| 2023 | 28 | 5.5 days | 11 days | 15 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Easy Permit Process timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Kenwood | 1 day | 12 days | 226 |
| Pullman | 1 day | 12 days | 109 |
| Albany Park | 0 days | 0 days | 529 |
| Archer Heights | 0 days | 7 days | 126 |
| Armour Square | 0 days | 0 days | 126 |
| Ashburn | 0 days | 10 days | 559 |
| Auburn Gresham | 0 days | 0 days | 747 |
| Austin | 0 days | 0 days | 1,240 |