Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Express Permit Program permits in Norwood Park

The typical express permit program permit issued in Norwood Park took 0 days. The 75th-percentile wait was 6 days.

Records checked1,1272021–Sep. 15, 2026

The short answer

Typical wait0 daysmedian issued permit
Usually within6 days75% of records
Long-wait edge16 days90% of records
Evidence1,127issued permits

The median was 1 day faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
51.2%
1–7 days
29.1%
8–30 days
15.4%
31–90 days
2.9%
91+ days
1.4%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211200 days3 days13 days
20221320 days5 days23 days
20231510 days2 days8 days
20242601 day6 days17 days
20252691 day6 days16 days
2026*1952 days7 days16 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Archer Heights0 days5 days424
Armour Square0 days3 days275
Ashburn0 days5 days1,434
Avalon Park0 days5 days586
Belmont Cragin0 days6 days1,245
Calumet Heights0 days5 days647
Chicago Lawn0 days6 days1,219
Dunning0 days4 days978