Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Express Permit Program permits in Morgan Park

The typical express permit program permit issued in Morgan Park took 0 days. The 75th-percentile wait was 6 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked8762021–Sep. 15, 2026

The short answer

For Express Permit Program permits in Morgan Park, 876 issued permit records show a median processing time of 0 days; 75% were issued within 6 days and 90% within 18 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within6 days75% of records
Long-wait edge18 days90% of records
Evidence876issued permits

The median was unchanged from the previous 12 months.

Express Permit Program permits in Morgan Park: wait distribution

For Express Permit Program permits in Morgan Park, 876 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
52.3%
1–7 days
26.9%
8–30 days
15.6%
31–90 days
4.3%
91+ days
0.8%

Change over time

Express Permit Program permits in Morgan Park: annual permit timing

Express Permit Program permits in Morgan Park has 6 publishable issue-year cohorts spanning 2021–2026, representing 876 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211180 days1 day8.6 days
20221020 days0 days4 days
2023900 days1 day22 days
20241631 day8 days17 days
20252382 days9.8 days25 days
2026*1651 day7 days16 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in Morgan Park: Express Permit Program timing in comparable community areas

Express Permit Program permits in Morgan Park has 876 issued records, a 0 days median, and a 6 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Archer Heights0 days5 days424
Armour Square0 days3 days275
Ashburn0 days5 days1,434
Avalon Park0 days5 days586
Belmont Cragin0 days6 days1,245
Calumet Heights0 days5 days647
Chicago Lawn0 days6 days1,219
Dunning0 days4 days978