Signs permits in Montclare

The typical signs permit issued in Montclare took 48 days. The 75th-percentile wait was 66 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked442021–Sep. 15, 2026

The short answer

For Signs permits in Montclare, 44 issued permit records show a median processing time of 48 days; 75% were issued within 66 days and 90% within 123 days, covering January 2021 through September 15, 2026.

Typical wait48 daysmedian issued permit
Usually within66 days75% of records
Long-wait edge123 days90% of records
Evidence44issued permits

Not enough records for a year-over-year comparison.

Signs permits in Montclare: wait distribution

For Signs permits in Montclare, 44 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
2.3%
1–7 days
11.4%
8–30 days
15.9%
31–90 days
56.8%
91+ days
13.6%

Change over time

Signs permits in Montclare: annual permit timing

Signs permits in Montclare has 1 publishable issue-year cohorts spanning 2025–2025, representing 19 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20251948 days52 days66 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs permits in Montclare: Signs timing in comparable community areas

Signs permits in Montclare has 44 issued records, a 48 days median, and a 66 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Montclare48 days66 days44
Near South Side48 days112 days127
Grand Boulevard46 days125 days76
West Garfield Park53 days82 days31
Loop38 days77 days662
Jefferson Park37 days64 days89
Lincoln Square37 days150 days197
Greater Grand Crossing35 days71 days57