Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Signs permits in Lincoln Park

The typical signs permit issued in Lincoln Park took 35 days. The 75th-percentile wait was 77 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked6392021–Sep. 15, 2026

The short answer

For Signs permits in Lincoln Park, 639 issued permit records show a median processing time of 35 days; 75% were issued within 77 days and 90% within 121 days, covering January 2021 through September 15, 2026.

Typical wait35 daysmedian issued permit
Usually within77 days75% of records
Long-wait edge121 days90% of records
Evidence639issued permits

The median was 8 days faster than the previous 12 months.

Signs permits in Lincoln Park: wait distribution

For Signs permits in Lincoln Park, 639 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
0.5%
1–7 days
18.8%
8–30 days
28.0%
31–90 days
34.4%
91+ days
18.3%

Change over time

Signs permits in Lincoln Park: annual permit timing

Signs permits in Lincoln Park has 6 publishable issue-year cohorts spanning 2021–2026, representing 639 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20219624 days83 days108 days
20221269.5 days70 days122 days
2023776 days47 days81 days
202415946 days77 days149 days
202512546 days76 days108 days
2026*5640 days74 days122 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs permits in Lincoln Park: Signs timing in comparable community areas

Signs permits in Lincoln Park has 639 issued records, a 35 days median, and a 77 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Greater Grand Crossing35 days71 days57
Lincoln Park35 days77 days639
Edgewater34 days62 days181
Forest Glen33 days138 days55
Jefferson Park37 days64 days89
Lincoln Square37 days150 days197
Lower West Side33 days77 days169
Loop38 days77 days662