Official community area
Gage Park permit processing times
For 1,190 issued permits in Gage Park, the median processing time was 1 day; 75% were issued within 13 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Gage Park permit processing times, 1,190 issued permit records show a median processing time of 1 day; 75% were issued within 13 days and 90% within 57 days, covering January 2021 through September 15, 2026.
The median was 3 days slower than the previous 12 months.
Gage Park permit processing times: wait distribution
For Gage Park permit processing times, 1,190 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Gage Park permit processing times: annual permit timing
Gage Park permit processing times has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,190 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 234 | 0 days | 8.8 days | 27 days |
| 2022 | 228 | 0 days | 9 days | 26 days |
| 2023 | 232 | 0 days | 13 days | 56 days |
| 2024 | 206 | 4 days | 26 days | 87 days |
| 2025 | 139 | 4 days | 16 days | 61 days |
| 2026* | 151 | 8 days | 44 days | 119 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Gage Park permit processing times: Nearby points in the citywide timing distribution
Gage Park permit processing times has 1,190 issued records, a 1 day median, and a 13 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Albany Park | 1 day | 14 days | 2,213 |
| Archer Heights | 1 day | 14 days | 812 |
| Ashburn | 1 day | 10 days | 2,411 |
| Auburn Gresham | 1 day | 11 days | 3,290 |
| Austin | 1 day | 14 days | 5,647 |
| Belmont Cragin | 1 day | 13 days | 2,724 |
| Beverly | 1 day | 13 days | 1,644 |
| Burnside | 1 day | 9.5 days | 227 |
More Gage Park permit processing times comparisons
The Gage Park permit processing times cohort contains 1,190 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 0 daysEasy Permit Process 0 daysRenovation & Alteration 41 daysSigns 14 days