Signs permits in Chatham

The typical signs permit issued in Chatham took 20 days. The 75th-percentile wait was 35 days.

Records checked1322021–Sep. 15, 2026

The short answer

Typical wait20 daysmedian issued permit
Usually within35 days75% of records
Long-wait edge59 days90% of records
Evidence132issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
0.8%
1–7 days
31.8%
8–30 days
34.1%
31–90 days
23.5%
91+ days
9.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021402.5 days7.2 days17 days
2022136 days54 days54 days
20232228 days38 days105 days
20241347 days174 days174 days
20253030 days30 days35 days
2026*1434 days35 days44 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs timing in comparable community areas

ReportMedian75% withinRecords
Chatham20 days35 days132
Hyde Park20 days49 days122
Mount Greenwood21 days41 days55
New City20 days54 days126
North Center20 days46 days252
North Lawndale20 days44 days75
Portage Park20 days44 days265
Washington Heights20 days74 days88