Community area × permit type

Signs permits in Chatham

The typical signs permit issued in Chatham took 20 days. The 75th-percentile wait was 35 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1322021–Sep. 15, 2026

The short answer

For Signs permits in Chatham, 132 issued permit records show a median processing time of 20 days; 75% were issued within 35 days and 90% within 59 days, covering January 2021 through September 15, 2026.

Typical wait20 daysmedian issued permit
Usually within35 days75% of records
Long-wait edge59 days90% of records
Evidence132issued permits

Not enough records for a year-over-year comparison.

Signs permits in Chatham: wait distribution

For Signs permits in Chatham, 132 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
0.8%
1–7 days
31.8%
8–30 days
34.1%
31–90 days
23.5%
91+ days
9.8%

Change over time

Signs permits in Chatham: annual permit timing

Signs permits in Chatham has 6 publishable issue-year cohorts spanning 2021–2026, representing 132 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
2021402.5 days7.2 days17 days
2022136 days54 days54 days
20232228 days38 days105 days
20241347 days174 days174 days
20253030 days30 days35 days
2026*1434 days35 days44 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs permits in Chatham: Signs timing in comparable community areas

Signs permits in Chatham has 132 issued records, a 20 days median, and a 35 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Chatham20 days35 days132
Hyde Park20 days49 days122
Mount Greenwood21 days41 days55
New City20 days54 days126
North Center20 days46 days252
North Lawndale20 days44 days75
Portage Park20 days44 days265
Washington Heights20 days74 days88