Signs permits in Avalon Park
The typical signs permit issued in Avalon Park took 22 days. The 75th-percentile wait was 33 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Signs permits in Avalon Park, 33 issued permit records show a median processing time of 22 days; 75% were issued within 33 days and 90% within 176 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
Signs permits in Avalon Park: wait distribution
For Signs permits in Avalon Park, 33 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Signs permits in Avalon Park: annual permit timing
Signs permits in Avalon Park has 1 publishable issue-year cohorts spanning 2025–2025, representing 14 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2025 | 14 | 22 days | 43 days | 99 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Signs permits in Avalon Park: Signs timing in comparable community areas
Signs permits in Avalon Park has 33 issued records, a 22 days median, and a 33 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Albany Park | 22 days | 74 days | 140 |
| Avalon Park | 22 days | 33 days | 33 |
| Chicago Lawn | 22 days | 81 days | 121 |
| Kenwood | 22 days | 52 days | 30 |
| West Lawn | 22 days | 50 days | 83 |
| Ashburn | 23 days | 71 days | 151 |
| Mount Greenwood | 21 days | 41 days | 55 |
| West Elsdon | 23 days | 97 days | 52 |
More Signs permits in Avalon Park comparisons
The Signs permits in Avalon Park cohort contains 33 issued records; related links retain separate location and permit-category cohorts.
All Avalon Park permits Area reportSigns citywide Type report