ZIP code × permit type
Easy Permit Process permits in ZIP 60661
The median easy permit process permit wait in ZIP 60661 was 0 days, based on 135 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Easy Permit Process permits in ZIP 60661, 135 issued permit records show a median processing time of 0 days; 75% were issued within 0 days and 90% within 4.6 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
Easy Permit Process permits in ZIP 60661: wait distribution
For Easy Permit Process permits in ZIP 60661, 135 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Easy Permit Process permits in ZIP 60661: annual permit timing
Easy Permit Process permits in ZIP 60661 has 3 publishable issue-year cohorts spanning 2021–2023, representing 135 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 45 | 0 days | 0 days | 7 days |
| 2022 | 55 | 0 days | 0 days | 2.2 days |
| 2023 | 35 | 0 days | 0.5 days | 4.6 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Easy Permit Process permits in ZIP 60661: Easy Permit Process timing in comparable ZIP codes
Easy Permit Process permits in ZIP 60661 has 135 issued records, a 0 days median, and a 0 days 75th-percentile wait in this release.
More Easy Permit Process permits in ZIP 60661 comparisons
The Easy Permit Process permits in ZIP 60661 cohort contains 135 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60661 permits ZIP reportEasy Permit Process citywide Type report