Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Easy Permit Process permits in ZIP 60620

The median easy permit process permit wait in ZIP 60620 was 0 days, based on 1,151 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,1512021–Sep. 15, 2026

The short answer

For Easy Permit Process permits in ZIP 60620, 1,151 issued permit records show a median processing time of 0 days; 75% were issued within 0 days and 90% within 12 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within0 days75% of records
Long-wait edge12 days90% of records
Evidence1,151issued permits

Not enough records for a year-over-year comparison.

Easy Permit Process permits in ZIP 60620: wait distribution

For Easy Permit Process permits in ZIP 60620, 1,151 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
76.8%
1–7 days
5.2%
8–30 days
16.9%
31–90 days
0.8%
91+ days
0.3%

Change over time

Easy Permit Process permits in ZIP 60620: annual permit timing

Easy Permit Process permits in ZIP 60620 has 3 publishable issue-year cohorts spanning 2021–2023, representing 1,149 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20214570 days0 days9.4 days
20223920 days1 day13 days
20233000 days0 days13 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Easy Permit Process permits in ZIP 60620: Easy Permit Process timing in comparable ZIP codes

Easy Permit Process permits in ZIP 60620 has 1,151 issued records, a 0 days median, and a 0 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606030 days5 days93
ZIP 606050 days3.8 days230
ZIP 606060 days2 days247
ZIP 606070 days1 day522
ZIP 606080 days0 days756
ZIP 606090 days0 days660
ZIP 606100 days6 days521
ZIP 606120 days0 days539