Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Wrecking & Demolition permits in West Town

The typical wrecking & demolition permit issued in West Town took 0 days. The 75th-percentile wait was 55 days.

Records checked2852021–Sep. 15, 2026

The short answer

Typical wait0 daysmedian issued permit
Usually within55 days75% of records
Long-wait edge91 days90% of records
Evidence285issued permits

The median was 46 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
62.1%
1–7 days
1.4%
8–30 days
3.5%
31–90 days
22.5%
91+ days
10.5%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20216343 days72 days98 days
2022480 days59 days105 days
2023430 days0 days0 days
2024480 days0 days60 days
2025420 days0 days0 days
2026*4155 days76 days91 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Wrecking & Demolition timing in comparable community areas

ReportMedian75% withinRecords
Albany Park0 days67 days28
Auburn Gresham0 days28 days44
Austin0 days50 days88
Avondale0 days38 days55
Bridgeport0 days50 days63
Chicago Lawn0 days0 days33
East Garfield Park0 days43 days33
Edgewater0 days49 days49