Community area × permit type
Wrecking & Demolition permits in West Pullman
The typical wrecking & demolition permit issued in West Pullman took 0 days. The 75th-percentile wait was 67 days.
Records checked1032021–Sep. 15, 2026
The short answer
Typical wait0 daysmedian issued permit
Usually within67 days75% of records
Long-wait edge125 days90% of records
Evidence103issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 32 | 68 days | 107 days | 170 days |
| 2022 | 13 | 0 days | 151 days | 222 days |
| 2025 | 26 | 0 days | 0 days | 0 days |
| 2026* | 16 | 59 days | 70 days | 76 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Wrecking & Demolition timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Albany Park | 0 days | 67 days | 28 |
| Auburn Gresham | 0 days | 28 days | 44 |
| Austin | 0 days | 50 days | 88 |
| Avondale | 0 days | 38 days | 55 |
| Bridgeport | 0 days | 50 days | 63 |
| Chicago Lawn | 0 days | 0 days | 33 |
| East Garfield Park | 0 days | 43 days | 33 |
| Edgewater | 0 days | 49 days | 49 |