Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Wrecking & Demolition permits in Logan Square

The typical wrecking & demolition permit issued in Logan Square took 0 days. The 75th-percentile wait was 64 days.

Records checked1972021–Sep. 15, 2026

The short answer

Typical wait0 daysmedian issued permit
Usually within64 days75% of records
Long-wait edge100 days90% of records
Evidence197issued permits

The median was 28 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
60.4%
1–7 days
0.0%
8–30 days
2.5%
31–90 days
24.9%
91+ days
12.2%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20214971 days90 days107 days
2022390 days65 days90 days
2023290 days0 days23 days
2024380 days0 days0 days
2025230 days0 days0 days
2026*1947 days80 days119 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Wrecking & Demolition timing in comparable community areas

ReportMedian75% withinRecords
Albany Park0 days67 days28
Auburn Gresham0 days28 days44
Austin0 days50 days88
Avondale0 days38 days55
Bridgeport0 days50 days63
Chicago Lawn0 days0 days33
East Garfield Park0 days43 days33
Edgewater0 days49 days49