Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Elevator Equipment permits in Lake View

The typical elevator equipment permit issued in Lake View took 0 days. The 75th-percentile wait was 0 days.

Records checked2682021–Sep. 15, 2026

The short answer

Typical wait0 daysmedian issued permit
Usually within0 days75% of records
Long-wait edge5 days90% of records
Evidence268issued permits

The median was unchanged from the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
77.2%
1–7 days
19.8%
8–30 days
2.6%
31–90 days
0.0%
91+ days
0.4%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021400 days0.2 days6.1 days
2022430 days0 days5 days
2023430 days0 days5 days
2024540 days0 days5 days
2025500 days0 days7.5 days
2026*380 days5 days5 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Elevator Equipment timing in comparable community areas

ReportMedian75% withinRecords
Armour Square0 days0 days35
Ashburn0 days0 days32
Auburn Gresham0 days0 days64
Austin0 days0 days126
Avondale0 days0 days29
Belmont Cragin0 days0 days47
Beverly0 days0 days33
Bridgeport0 days0 days45